Un passo avanti nel decommissioning nucleare italiano: Sogin ha completato con successo il collaudo della nuova "Scatola a Guanti" SAG-CEM, l'impianto prototipo realizzato da un RTI composto da Orano e Fucina Italia.A step forward for Italian nuclear decommissioning: Sogin has successfully completed the testing of the new SAG-CEM glovebox, the prototype plant built by a temporary consortium of Orano and Fucina Italia.
0,8 m³
Rifiuti liquidi da cementareLiquid waste to be cemented
3
Moduli che compongono il sistemaModules making up the system
2027
Avvio delle attività di condizionamentoStart of conditioning operations
Il collaudo
Sogin ha completato con successo il collaudo della nuova "Scatola a Guanti" (SAG-CEM), un impianto prototipo innovativo progettato interamente dalla società per trattare rifiuti radioattivi liquidi di media attività contenenti plutonio e uranio presso l'Impianto Plutonio (IPU) del Centro Ricerche Casaccia di Roma.
Il sistema
Il sistema — realizzato da un RTI composto da Orano e Fucina Italia — è articolato in tre moduli e consentirà di cementare circa 0,8 m³ di rifiuti liquidi prodotti dalle attività storiche di fabbricazione del combustibile nucleare. Il processo è completamente confinato e isolato dall'ambiente esterno, garantendo il massimo livello di sicurezza per i lavoratori.
Il contributo di Fucina Italia
Fucina Italia ha realizzato la SAG-CEM insieme ad Orano, mettendo a disposizione le proprie capacità produttive e ingegneristiche per ambienti confinati e attrezzature per la manipolazione di materiali radioattivi. Leggi il nostro articolo sul progetto →
I prossimi passi
Le attività di condizionamento partiranno nel 2027. I manufatti prodotti saranno conservati in sito in attesa del conferimento al futuro Deposito Nazionale.
The testing
Sogin has successfully completed the testing of the new SAG-CEM glovebox, an innovative prototype plant designed entirely by the company to treat intermediate-level liquid radioactive waste containing plutonium and uranium at the Plutonium Plant (IPU) of the Casaccia Research Centre in Rome.
The system
The system — built by a temporary consortium of Orano and Fucina Italia — consists of three modules and will cement around 0.8 m³ of liquid waste produced by past nuclear fuel fabrication activities. The process is fully confined and isolated from the outside environment, ensuring the highest level of safety for workers.
Fucina Italia's contribution
Fucina Italia built SAG-CEM together with Orano, contributing its manufacturing and engineering capabilities for confined environments and equipment for handling radioactive materials. Read our article on the project →
Next steps
Conditioning operations will start in 2027. The resulting packages will be stored on site pending transfer to the future National Repository.
Un tassello importante nel percorso di messa in sicurezza del patrimonio nucleare italiano.An important step in making Italy's nuclear legacy safe.
Fucina Italia Srl — Piombino
Articolo originaleOriginal Article
Questo articolo è tratto dall'agenzia ANSA del 17 settembre 2026. Per leggere il testo completo visita il link qui sotto.This article is sourced from the ANSA agency dated September 17, 2026. To read the full text, visit the link below.
Questo sito utilizza esclusivamente cookie tecnici necessari al suo funzionamento.
Non vengono utilizzati cookie di profilazione o di terze parti a scopo pubblicitario.
Per maggiori informazioni consulta la nostra
Privacy & Cookie Policy.